Gilliland CM has been hard at work with a great client to construct a new wellness center in Oceanside. The new building is currently nearing completion on the shell. Interior work has begun on the 3rd and 2nd floors for the electrical, mechanical and fire protections services. The parking garage is also nearing shell completion and is scheduled for completion by the end of July. The ground up project consists of approximately 90,000sf of office space in a new three story concrete tilt up building. The project is anticipated to be occupied by the end of 2020.