This past weekend the mat slab was poured for the new six story high-rise being built at 450 B St. The pour took over nine hours with a crew of 20 men and included approximately 80 trucks 750 yd.³ of concrete that’s approximately 3,000,000 pounds of concrete and 100,000 pounds of rebar.

Developer: LeBeau Realty Associates

General Contractor: CW Driver

Architect: Gensler

Structural engineer: Coffman Engineers

Alternative Text

By Kirt Gilliland

Feb 27, 2020